The Hon. Greg Combet AM MP
Minister for Defence Personnel, Materiel and Science
UPDATE
ON AIR WARFARE DESTROYER PROJECT
Greg
Combet, Minister for Defence Personnel, Materiel and Science, announced today
that
During
a visit to
The
AWDs are being constructed using the block method, with 30 per cent of the
blocks being made at ASC in
Similar
fabrication of blocks will commence in November at BAE’s facilities in
“Successful
completion of pilot blocks is a key step in the move to full-scale production
of the three AWDs and demonstrates that the project is successfully moving from
the design to construction phase,” Mr Combet said.
Mr
Combet also said today Australian companies were continuing to demonstrate
their ability to win work on the AWD project.
The
AWD Alliance has recently signed six contracts worth approximately $18 million
with Australian companies for the supply of a wide range of services and
equipment for the three Air Warfare Destroyers.
“Scientific
Management Associates has won a contract initially worth $13 million to supply
a range of integrated logistic support services to the project. This is crucial
work which will ensure the highly sophisticated AWDs are well supported to meet
the Navy’s operational requirements.”
Mr
Combet said five South Australian companies had also recently won work on the
AWD project.
“Ottoway
Engineering, based in
The
AWD Alliance has also signed a $12 million contract with Eurotorp for the
provision of the torpedo launch system for the three ships.
The
AWD Alliance is made up of the DMO, ASC as the shipbuilder and Raytheon
Media Contacts:
Rod
Hilton (Greg Combet): (02)
6277 7620 or 0458 276 619
Jim
Cannon (AWD
Defence
Public Affairs: (02)
6127 1999 or 0408 498 664